Due to bad weather, shelling and technological disruptions, consumers in 7 regions cut off from power supply
Consequences of bad weather
Due to adverse weather conditions, more than 2,000 consumers in Khmelnytskyi and Kirovohrad regions are cut off from electricity supply. Work is underway to restore power supply.
Power generation
Power generating facilities are operating normally. The coal and fuel oil stocks are sufficient for the uninterrupted operation of the plants.
The amount of electricity generated is sufficient to fully meet the consumer and industry demand.
One of the generating units is under short-term repair (within a day).
Situation in the frontline regions
Over the past day, almost 1,200 consumers in Donetsk region have had their electricity restored.
In Kharkiv region, several power lines that were de-energised as a result of hostilities have been reconnected to the grid.
As a result, 57 customers have been reconnected.
Some consumers in Donetsk, Zaporizhzhia, Sumy, Chernihiv, Kharkiv and Kherson regions remain without power supply.
Situation in the regions
In Kyiv region, 1,245 customers were cut off from power as a result of technological disruptions. Power engineers are working to restore power supply.
Situation at the ZNPP
The water level in the cooling pond remains unchanged at 15.68 metres.